Basement Finishing









Start date - March 8,   Finished  April  May 15  
June 5          Furniture & stuff
May 23         A few pictures
May 15         Finished!
May 12         First coat of Poly-Urethane
May 11         Mirror & a little more
May 10         Door handles, transition (9.5 weeks)
May 1           Counter top, bath work (8 weeks)
April 23       Cabinets & Trim (7 weeks)

April 17       Floors done (6 weeks)
April 14       Tiles done wood floor 1/3rd
April 10       Bathroom & Laundry room - tiles done

April 9         Paint - Tile work (5 weeks)
April 2         Texture & Entry done   (4 weeks)
March 30     Drywall
March 27     TV, Towel holder, TP holder extra
March 22     Framing
March 15     Rough Electrical, plumbing, heating
Feb 15          Ping-Pong Table


A few pictures
May 23 basement 1.jpg
                                                                      The Ping Pong table - the windows are done too!
May 23 basement 2.jpg May 23 basement 3.jpg May 23 basement 4.jpg
The windows have a film on them - it's vacuum attached (meaning you put water on the window, lay the film on top of it and squeegee out the air bubbles and water - can be easily replaced any time) we picked a bamboo designMay 23 basement 5.jpg
Ping Pong table from the other side


May 15       Finished
It's finished, finally! The inspector found couple of problems with Electrical and Plumbing (Electrical - need AFI protection on lights, power and fire alarms; Plumbing - need water hammer arresters for washing machine and dishwasher). So, perhaps another day's work and then another inspection.
Entry
Basement may 16 01.jpg Basement may 16 02.jpg Basement may 16 03.jpg
               looking from stairs                                                Top - arch and entry                                         Bottom - floor and window

Furnace & Water Heater
Basement may 16 05.jpg Basement may 16 06.jpg Basement may 16 07.jpg
                      Utility closet                                           overflow pan under water heater                              to the drain in floor
Bathroom
Basement may 16 08.jpg Basement may 16 09.jpg Basement may 16 10.jpg
 Toilet - access panels for main water shut-off                             Shower                                                 Inside shower with safety bar
           and water pressure controller

Basement may 16 11.jpg Basement may 16 12.jpg
                                  Vanity                                                                                                    Mirror, lights & Medicine Cabinet
Laundry
Basement may 16 13.jpg Basement may 16 14.jpg
              Laundry room - washer & dryer - racks - wide-side                                            storage rack - narrow-side
Storage
Basement may 16 15.jpg Basement may 16 16.jpg
                           Large area under the stairs                                                                                  Narrow area
Bar
Basement may 16 17.jpg
  Monika cleaned it and decorated it for her face-book page
Studio
Basement may 22 01.jpg Basement may 22 02.jpg Basement may 22 03.jpg
                        Studio entrance                                             Main Painting wall                                        Secondary painting wall
Ping Pong
   Basement may 22 04.jpg
Will install the net and window coverings and post another picture later
Fixes
Basement may 22 05.jpg Basement may 22 06.jpg Basement may 22 07.jpg
  water hammer arresters for washing machine                       and dishwasher                                 Electric sub-panel for AFI protection
                                                                                                                                                           Originally he had used the main panel for all
                                                                                                                                                              the new wiring also, but had to change it.


May 12  First coat of Poly-urethane done
One more coat and it's all done except for fixing the crawl space access in the studio, turning the dishwasher on and a few touch ups.
Basement May 12 01.jpg Basement May 12 02.jpg Basement May 12 03.jpg
                           Entry way                                                       Ping Pong area                                                        Bar area


May 11      Mirror & a little more
For a change they worked around 8 hours today and installed the bathroom mirror along with a couple other things and hooked up everything (dishwasher, garbage disposal etc.) They are planning to touch-up and finish everything and put the first coat of poly-urethane today, followed by another coat tomorrow - and that should be the end of everything except - one side panel of the cabinets (missed in ordering; now waiting for it to arrive) and bar-area back splash - glass & mirror tiles - being designed by Monika)
Basement May 11 01.jpg Basement May 11 03.jpg Basement May 11 02.jpg
           Pan under the water heater                                                      Mirror                                Handle on tile to access crawl space (laundry
 to control water spillage in case of heater failure                                                                                 room)
for plumbing work etc.


 
May 10    Lazy lazy lazy 
They are now working very slowly - usually, just one person shows up for 3 or 4 hours and does one or two things. I still owe them almost $5,000 and very little work is left to do - so, I don't understand what the heck is wrong with these people. One day, I took the lone worker - Fabian, to the store (Lowes) and bought door handles and transition strips; another day we bought the bathroom mirror at Target (not installed yet). In the last ten days a few things have been done - like installing door handles and transitions (good that I bought them); today they installed the window sills and the granite splash-back.  The biggest piece of work done, last week,  was - sanding the floor to get rid of the black marks in the wood floor. The biggest piece of work left to do is to put the poly-urethane coating on the floor (two coats); rest is minor work like hooking up the dishwasher, filling holes and retouching paint and stuff like that.
Basement May 10 01.jpg Basement May 10 02.jpg Basement May 10 03.jpg
                                Access to Sprinkler                            door opener (furnace room)                       door opener (close-up)
Basement May 10 04.jpg Basement May 10 05.jpg Basement May 10 06.jpg
    Door handles - storage under the steps                         Transition strip - laundry room                  hole fixed - needs texture work
Basement May 10 07.jpg Basement May 10 08.jpg
               Window sill (need to paint the whole thing white)                     Back-splash installed and faucet, garbage disposal, Dishwasher
                                                                                                                       connected (need to check them to make sure they all work)    
Note: The wall under the counters will have a glass tile back-splash - being designed by Monika (not sure what she wants)                                                  


May 1  Counter top, bath area (8 weeks)
They installed the counter top & sink in the bar area, most of the fixtures in the bath area, the doors on the utility area and not much else.
Left to do - connect the dishwasher, install faucet and garbage disposal in the bar area, connect the toilet & install faucet in the bathroom; sand and finish wood floor; install door handles, fill/finish transition areas; install window sills; and do other touch ups (cracks and holes). Hoping they finish next week.
Basement May 1 01.jpg Basement May 1 03.jpg Basement May 1 02.jpg
       Toilet & Shower installed,  light installed (middle one left out - need to fill the cracks in the tiles); vanity, top & sink installed
Basement May 1 04.jpg Basement May 1 05.jpg Basement May 1 06.jpg
        Granite counter top and sink installed                      sliding doors - furnace area                         doors for storage under the stairs



April 23  Cabinets & Trim (7 weeks)

OK! Tony got lazy or sidetracked this week and didn't do much this week. But today (Friday) it's been raining all day and tomorrow it's supposed to snow - so they can't work outside (if they have another job); they worked a lot today here and I hope tomorrow too. Still to do -sand and finish the floors; install fixtures in the bath; counter top (+ sink & garbage disposal) and faucet in the bar area. Hopefully no more than one more week!

Basement April 23 01.jpg Basement April 23 02.jpg
Cabinets & wine rack with glass holder - old dishwasher (not connected)                         trim around the walls, doors and rooms
Basement April 23 03.jpg Basement April 23 04.jpg
          Laundry room door (old entry door re-used)                                                                      Medicine cabinet
Need to install shower, shower walls & door, toilet, vanity, vanity top, sink, mirror & light in the bathroom



April 17   floor done (6 weeks)

Basement April 17 01.jpg  Basement April 17 02.jpg  Basement April 17 03.jpg
     from the bar area to the ping-pong area              from the bar area to the bathroom                                      Entry       

All that is left to do - sand and finish the floors; hang doors and nail trims; install fixtures in the bath; cabinets, counter top and dishwasher in the bar area. One more week to go!




April 14  Tiles done wood floor 1/3 done
Basement April 14 01.jpg Basement April 14 04.jpg Basement April 14 05.jpg
                                  Studio tiles (darker)                                        Storage area under stairs                    Storage area under stairs (2) 
Basement April 14 02.jpg  Basement April 13 01.jpg  Basement April 14 03.jpg                     Ping-Pong area                                          Felt-Paper under the wood floor                                   Hickory tiles (close up)

All the tiles and grout are done and the floor is about 1/3rd done. They will sand and finish (urethane) it when its all laid out.  And then install trims and doors and bathroom fixtures, bar area cabinets and counter top and it will be all done (2 weeks or a little less).



April 10  Bathroom & Laundry room - tiles done

Basement April 10 01.jpg  Basement April 10 02.jpg
                               Bathroom - shower side wall                                                                            Sink side wall
Basement April 10 03.jpg  Basement April 10 04.jpg
  Laundry room (the end tiles are on the crawl-space access panel)                                              laundry room -angled corner



April 9  Paint done, Tile work started
Basement April 9 01.jpg Basement April 9 02.jpg Basement April 9 03.jpg
            Tile floor bottom-board (water resistant)                              Entry way                           Bathroom tiles on one wall (access for water
                                                                                                                                                                shut-off and pressure controller)

Basement April 9 04.jpg  Basement April 9 05.jpg
                             The sink area                                                                                            shower & sink area


April 2   Texture & Entry done

Basement April 2 01.jpg  Basement April 2 02.jpg
               The door and wall is removed and an arched entry made;                       entry and utility area (compare with before)

Basement April 2 03.jpg  Basement April 2 04.jpg
                                   New outlet for fridge added (compare with before)               Bathroom walls (Dura rock - cement board)



March 30  drywall done

Basement March 29 01.jpg Basement March 29 02.jpg Basement March 29 03.jpg
          Bathroom and laundry room                             The ceiling inside the laundry area              The two storage areas (under the stairs)
Basement March 29 04.jpg Basement March 29 05.jpg Basement March 29 06.jpg
                                             Storage areas under the stairs                                                                        bar area (missing outlet for fridge)
Basement March 29 07.jpg Basement March 29 08.jpg Basement March 29 09.jpg
                          Bar area                                                           Ping-Pong area                              entry and utility (furnace and water heater)
                                                                                                                                                           the door will be removed and an arched
                                                                                                                                                           entry
made later on. (here for finished entry)
Basement March 29 10.jpg Basement March 29 11.jpg Basement March 29 12.jpg
             Ping-Pong area - Studio on the left                             Inside the studio                                             Studio and utility room



March 27  some extras
                 Having talked to Ajay for a while on the basement project, he had mentioned a ton of things; among those that I got done were some 2 by 4 pieces of wood installed where the toilet paper holder and the towel holders go in the bathroom as well as where the TV may go in the bar/entertainment area.
Basement March 27 01.JPG Basement March 27 03.JPG Basement March 27 06.JPG Basement March 27 07.JPG
  2 by 4s nailed to mount the TV over the storage area & the bar area               2 by 4 for the towel holder         & for the tp holder


March 22  Framing
                  On March 22nd, the framing was all done. The first inspections and approvals were done over the next few days; the framing was approved on March 29th and the dry walls started.  A few pictures showing the framing:
Basement March 22 01.JPG Basement March 22 02.JPG Basement March 22 03.JPG Basement March 22 04.JPG
          Bathroom framing                       lights, wiring, framing                              exhaust fan                           rough bath

Basement March 22 05.JPG Basement March 22 06.JPG Basement March 22 07.JPG Basement March 22 08.JPG
                                                                                                  Heating and lights

There is also a video on March 22nd showing all the framing etc. to locate pipes etc. later on, though its pretty hard to figure out how one does that - will see if and when its really needed. The video is here - Its large 320 MB so only click on the link if you have broadband video Basement March22.
I found super quiet exhaust fans on the internet (0.4 sones) and had them install one in the basement bathroom, the other two I was going to try and do myself on the main floor. When I looked in the attic, I gave up on doing it myself. The same guy will install them later in the main floor bathrooms too.



March 15 & 16   Rough Electrical, Plumbing & Heating
                  I took a video before anything was done on February 28th. The video is large 190 MB - so click here only if you have broadband  video 1 February 28.
The work started on March 8th and I took some pictures after a week on March 15th. Basically rough electrical, rough plumbing and rough heating work was done by then. A few pictures show all of the rough work:
basement march 15  01.JPG basement march 15  02.JPG basement march 15  03.JPG basement march 15  04.JPG
       Laundry room heating pipes                    Open area - lights               Lights near the entry way       Heating pipe for Bathroom


basement march 15  05.JPG basement march 15  06.JPG  basement march 15  07.JPG basement march 15  08.JPG
       Existing Return air                        lights in the Ping-Pong area                  lights  bar area                          some electric outlets  bar area

I also took a video on March 14th showing the rough work -
The video is also large 93.7 MB - so click here only if you have broadband  video 2 March 14.



Pictures from March 16
basement march 16 01.JPG basement march 16 02.JPG basement march 16 04.JPG basement march 16 05.JPG
            Heating vent - Laundry                          lights, heating vents                     plumbing                             light under stairs

basement march 16 06.JPG basement march 16 07.JPG  basement march 16 08.JPG basement march 16 09.JPG
                light under stairs                                                          electric and heating



February 15 Ping-Pong Table
                      At First we thought that we have to move the furnace and Water heater to make room for the Ping-Pong table. The suggested space is 6 feet on each side. A standard Ping-Pong table is 9 feet by 5 feet, so one would need 21 feet (9+6+6) by 17 feet. We have almost 24 feet for the length of the table but were not sure about the width and how much space we really need for it.  We have about 3.5 feet on each side unless we move the furnace, then we would have 19 feet or 7 feet on each side (width).  We got some estimates on finishing the basement which included moving the furnace and heater; they ranged from $10,500 to $21,000. In the meantime, I bought a full size Kettler Ping-Pong table and we assembled it in the basement and placed it in the area and it seems to work fine with just 3.5 feet on each side - width-wise. Length-wise you do need at least 6 feet on each end (we have 7.5 feet and it's good to have that little bit extra).


bsmnt_001.jpg bsmnt 002.jpg
    Length-wise it's fine.                                                                              Width-wise it's adequate

 

home

 

 

 

 

 

 

Copyright © 2005 Raman Jalota. All rights reserved. No part of this electronic publication may be reproduced, stored in a retrieval system or transmitted in any form or by any means, electronic, mechanical, recording or otherwise, without the written permission of the author.